Brief schedule of Phase 1

Time scale Activity
Months 1-5 - Contact with Learning Providers
- Development of learning infrastructure (ongoing throughout project)
- MerseyWorkPlace made available on digital TV (Telewest)
Month 5 Project Information Meeting for potential Learning Providers.
Month 6 Interested Providers complete course proposal
Months 6 -8 Negotiation process with Providers (viability of proposal and of meeting expressed needs)
Months 7-8 - Selection of participants - reaching agreement on collaboration
- Discussion with Providers regarding system capabilities and provider requirements
- Providers' contribution to system design
Mont h 9 - Learning Provider Questionnaire 1 - collecting baseline information from Providers
- Learning Provider Information Meeting
- Learner trials (usability test with potential learners)
Month 10 Launch of CourseMaker
CourseMaker Training for Learning Providers
Month 13 - Launch of administration system
- Plan of action agreed with LPs
- Launch of TeLP on idTV
Months 10-15 Bulk of content development, ELO support and monitoring, including observation of learner sessions
Months 16-17 Data collection from LPs (LPQ3, LP interviews)
Months 15-18 Collecting data from learners (ERDF, questionnaires, interviews)
Months 15-18 Report writing (Best Practice and Research Report)
Month 18 200 Merseyside beneficiaries accessed 10 TeLP courses
Interim Research Report
Interim Best Practice Guide